Installing the Gunnebo SpeedStile FL requires careful site preparation and precise alignment to ensure the security barriers function correctly. This guide provides a summary of the essential steps for installing the SpeedStile FL , including the FLS BA and EV variants. 1. Site Preparation and Foundation
The structural integrity of the installation site is the responsibility of the customer. Ensure the following before beginning:
Floor Quality: The finished floor must be flat and level within ± 5mm.
Foundation Depth: Use concrete with a minimum resistance of fckcube 30N/mm². The minimum bolting depth for anchors is 70mm.
Conduits: Run cables at least 140mm below the finished floor level, rising at least 50mm from the foundation. 2. Pedestal Positioning and Alignment
Correct alignment is critical for the system's sensors and flap leaves to operate properly.
Mark Alignment: Use a chalk line on the floor to mark the placement of the units.
Identify Units: Distinguish between Left (L), Right (R), and Center (C) cabinets to create the desired number of lanes.
Identify Master/Slave: For multiple lanes, identify Master and Slave pedestals. The Master unit typically contains the LCM02 board and a circuit breaker above the transformer.
Placement: Position units to be perfectly parallel. The Master unit should ideally be on the secure (exit) side of the lane. 3. Mechanical Installation gunnebo speedstile fl installation manual
Drill Fixing Holes: Once aligned, mark the fixing hole positions, move the units, and drill into the floor.
Anchor and Level: Reposition the units and secure them with anchors. Use shims to ensure the frame is perfectly level in both longitudinal and transverse directions.
Install Components: Attach flap leaves to the rotor drive column and install lids and covers once wiring is complete. SpeedStile FLs BA|EV - Protogetic
LAYOUT CONFIGURATION & STANDARD DIMENSIONS. Shown is the SpeedStile FLs Wide BA (square lid ends). The EV version (round lid ends) Protogetic SpeedStile
Gunnebo SpeedStile FL Installation Manual: A Comprehensive Guide
The Gunnebo SpeedStile FL is a popular access control solution used in various industries, including retail, transportation, and government. Its sleek design, high-speed capabilities, and advanced features make it an ideal choice for managing pedestrian traffic. However, to ensure a successful installation, it's essential to follow the manufacturer's guidelines and recommendations. In this article, we'll provide an in-depth look at the Gunnebo SpeedStile FL installation manual, covering the necessary steps, requirements, and best practices.
Pre-Installation Requirements
Before starting the installation process, make sure to:
Installation Steps
The Gunnebo SpeedStile FL installation manual provides a step-by-step guide for installing the gate, control unit, and other components. Here's an overview of the process:
Configuration and Testing
After completing the installation, follow these steps:
Maintenance and Troubleshooting
Regular maintenance and troubleshooting are essential to ensure the Gunnebo SpeedStile FL operates smoothly and efficiently. The manual provides guidance on:
Best Practices and Considerations
When installing the Gunnebo SpeedStile FL, keep in mind:
Conclusion
Gunnebo SpeedStile FL: Essential Installation & Setup Guide The Gunnebo SpeedStile FL (Flap Leaf) is a sophisticated speed gate designed to balance security with a high-flow pedestrian aesthetic. This guide synthesizes key technical requirements and procedural steps for professional installation, ensuring operational longevity and safety. 1. Site Preparation & Structural Requirements Installing the Gunnebo SpeedStile FL requires careful site
Before unboxing the units, the installation site must meet specific structural and environmental criteria:
Foundation Integrity: The mounting surface should be a flat, level concrete base (Concrete to BS 5328:1997 type ST5) with a minimum thickness of 150mm.
Surface Tolerance: The floor must be level within +/- 5mm over the entire footprint of the SpeedStile unit.
Mounting Depth: Anchor bolts require a minimum depth of 70mm into concrete with a resistance of at least 30N/mm².
Conduit Placement: All electrical conduits must be run at least 140mm below the finished floor level (FFL) and should rise a minimum of 50mm from the foundation into the cabinet. Gunnebo SpeedStile FL
REPORT: Gunnebo SpeedStile FL Installation Manual
Subject: Overview of Installation Procedures and Technical Specifications for Gunnebo SpeedStile FL Speed Gates.
Date: October 26, 2023 Prepared By: Technical Documentation Review
| Mode | Description | Use Case | | :--- | :--- | :--- | | Locked | Flaps remain closed; passage requires valid credential. | Secure entry during business hours. | | Unlocked | Flaps remain open; acts as a free passage. | Fire evacuation or lunch breaks. | | One-Way | Entry lane unlocked, exit lane locked. | Event check-in. | | Momentary Open | Flaps open for 5 seconds after valid card, then close. | High-security anti-tailgating. | Read the manual : Familiarize yourself with the
The SpeedStile FL rewards attention. Scheduled inspections prevent drift: tighten anchors seasonally, inspect seals and glass for micro-movements, check sensor alignment, and replace consumables before failure. Keep motor firmware and access-control integrations updated with change control and backups.